Facility Area:
Ground Floor: 650sqm
Mezzanine Floor: 175sqm
Timescales:
Scheme Design: Completed November 2011
Detail Design: Completed February 2010
Start on Site: March 2010
Handover: October 2010
Construction Value:
£4m
Project
Small Scale Solid Dose Manufacturing Facility, Refurbishment and Extension to M Building.
The facility incorporated Dispensing, Granulation, Blending, Compression and Coating Facilities, 2No Flexible Production Suites together with Ancillary GMP Storage Facilities, and an IBC Bin Wash Facility.
Scope of Services
Simons acted as Lead Consultant to develop Concept, Scheme and Detail Design proposals and provided technical support throughout the pre construction and construction phases, to handover.