Facility Area
Laboratories: 750sqm
Write Up and Meeting Rooms: 650sqm
Timescales
Detail Design: Completed June 2014
Start on Site: June 2014
Handover: December 2014
Contract Value
The contract Value of the building works excluding equipment was £3.5m.
Project
Relocation of Bio Pharm Innovations from existing Facilities in Cambridge to new Facilities on the GSK Campus at Stevenage. The project involved the remodelling and refurbishment of existing Laboratory and Write Up Facilities to form new bespoke facilities for the Bio Pharm Innovations Team.
Scope of Services
Simons Design provided architectural design services to develop Concept, Scheme and Detail Design proposals and provided technical support throughout the pre-construction and construction phases, to handover. The design proposals were developed in BIM to enable detailed coordination of the facility and services installation.