Facility Area
Ground Floor: 260sqm
First Floor: 135sqm
Timescales
Detail Design: Completed Sept 2014
Start on Site: January 2015
Handover: December 2015
Contract Value
The contract Value of the building works excluding equipment was £4.1m.
Project
New OSD Micronising Manufacturing Facility. The project involved the design of a new OSD Manufacturing Facility providing Grade D quality space, careful integration of the Equipment requirements was required to coordinate the equipment and facility requirements to ensure the production operations were fully considered within the facility design.
Scope of Services
Simons Design provided a multi-disciplinary design team to develop Concept, Scheme and Detail Design proposals and provided technical support throughout the pre-construction and construction phases, to handover. The design proposals were developed in BIM to enable detailed coordination of the equipment and services.